Since 1999, CPM implemented Quality Management System (QMS ISO 9000), Health and Safety Management System (OHSAS 18000), Environment Management System (EMS ISO 14000), QMS ISO 9001:2008, OHSAS 14001:2007 and EMS ISO 14001:2004. CPM has certified of the ISO 9001 : 2008, OHSAS 18001 : 2007 and ISO 14001 : 2004, issued by TUV Germany.
Home arrow Experiences
Pipeline Experiences

No 

Client

 

Project Title

 

Location

 

Scope of Work

Schedule

1

PT. Perusahaan Gas Negara (Persero) Tbk.

 

Pipeline Construction Contract Onshore Gas Pipeline (Muara Bekasi - Rawa Maju)

 

Muara Bekasi, West Java

 

Engineering, Procurement and Construction, 28” – 30 Km

 

Sep-06

Jul-07

                     

2

PT. Perusahaan Gas Negara (Persero) Tbk. / GEOCEAN

 

South Sumatra West Java Gas Pipeline Project Phase I - Pckg #2 Offshore Pipeline

 

Cilegon, Banten

 

Onshore Pipeline

 

Dec-05

Aug-05

                     

3

PERTAMINA DOH SUMBAGSEL / PT. IKPT

 

Pembangunan Fasilitas Gas dan Transmisi Sumatera Selatan (PPGS), Pipa Salur Gas dari Musi Barat s/d Pagardewa

 

Musi Barat – Pagadewa, Muara Enim, Sumatera Selatan

 

Construction and Pre-commissioning:

Ø 28" x 130 Km Gas Pipeline, Ø 32" x 45 Km Pipeline dan, Ø 6" x 45 Km Condensate LineInclude 4 of 28” HDD River Crossing and 1 of 32” HDD Public road through to Rail Road crossing

 

Oct-04

Feb-06

                     

4

PERUM GAS NEGARA (Persero)

 

Gas Transmission Project “Package A” Trunkline

 

Trans -
Central Sumatera

 

Detail Engineering. and Construction of 28” - 544 Km Gas Pipeline

 

Jan-98

Aug-99

                     

5

VICO Indonesia IPAS #

 

Installation of Mutiara - Tunu Transfer Oil Line Pipeline

 

Delta Mahakam,
East Kalimantan

 

Construction of The 10” – 52 Km
Swampy area and Shallow Water Offshore Area.

 

May-97

Dec-97

                     

6

Cikarang Listrindo / PT. Rabana Gasindo Utama

 

Pertamina - Cikarang Listrindo Gas Supply

 

Citarik - Cikarang,
West Jawa

 

Construction of 18” - 50 Km Gas Pipeline includes;
Bridge and Gathering Station

 

May-94

Apr-95

                     

7

PERTAMINA E.P. North Sumatera / PT.Moeladi

 

 

Penambahan Daya PLN dengan Pemanfaatkan Gas Sumetera

 

P. Brandan Station to Wampu
North Sumatera

 

•  Construction of 18” - 52 Km Gas Pipeline, Include; Plawi, Wampu and Sarangan River Crossing

•  Construction of 4” - 5.1 Km Gas Pipeline from SP. XV to SP XVI, Rantau Field.

•  Construction of 6” and 4” - 2.9 Km Gas Pipeline from SP. I to SP.III. Wampu Field.

•  Construction of 6” - 2 Km Gas Pipeline from Point C to SP.III.

•  Construction of 8”- 12.4 Km Gas Pipeline from P. Brandan to Point C.

•  Construction of 8” - 7 Km Gas Pipeline from P. Batu to SP.I

• Construction of 14” - 6.5 Km Pipeline from P. Brandan to P. Batu.

 

Aug-93

Nov-94

                     

8

PERTAMINA E.P. South Sumatera / PT.Moeladi

 

 

 

 

Pemasangan Pipa Gas Baru Ke PUSRI

 

Lembak - Pusri
South Sumatera

 

• Construction of Onshore Gas Pipeline (Continues sizes) :

•  14” – 52 Km Lembak- Simpang Y (40% Swampy Area)

•  22” – 20 Km Simpang Y - Plaju (Incl. Convent. 24 Mtr. National Road Crossing and Ogan - 600 M and Musi - 1,500 M River Crossings w/ HDD)

•  24” - 20 Km Plaju - PUSRI (Incl. 400 Mtr Komering River Crossing )

 

Jun-92

Oct-93

 
      
      